UPS load prioritization

UPS Load Priority Runtime Planner — Protect Critical Loads First

Group connected loads by priority and see how UPS autonomy changes when lower-priority equipment is shed.

UPS battery and load inputs

kWh nominal
% of nominal
%
hours

Loads

Priority 1 is treated as essential, Priority 2 as important and Priority 3 as discretionary. The planner assumes each entered load is constant during the modeled runtime.
Add the loads the UPS needs to support.

Why load shedding can extend UPS autonomy

UPS runtime is strongly affected by output load. Protecting only essential loads can substantially increase the time available for controlled shutdowns or continued operation.

Priority groups

Priority grouping makes the result operational rather than treating every connected device as equally important.

Runtime scenarios

The calculator reports runtime for Priority 1 alone, Priority 1+2, and all loads. These scenarios show exactly what autonomy is being exchanged for additional load support.

Planning interpretation

Compare each runtime with the required runtime. If the all-load scenario is too short but the essential-only scenario is adequate, a load-shedding strategy may be worth investigating.

Limitations

Actual UPS batteries have discharge-rate effects, aging, temperature dependence and manufacturer-specific usable capacity.

Frequently asked questions

Can two loads have the same priority?

Yes. The planner simply groups them together.

Can a load be zero?

Yes, although it contributes nothing to the runtime calculation.

Does this control the UPS?

No. It is a planning tool and does not send commands to equipment.