How condensate pipe fall is calculated

For a constant slope, elevation change is simply run length multiplied by the slope as a decimal.

Fall = Run × (Slope ÷ 100)
Downstream elevation = Starting elevation − Fall

Worked example

A 12 m run at 1% slope drops 0.12 m. Starting at 100.00 m gives a downstream elevation of 99.88 m.

Why the starting datum matters

A fall value is useful for routing, but the actual construction point must be tied to a consistent project datum. Small elevation differences can matter when working around ceilings, traps or equipment bases.

Limitations

This does not prescribe the required slope or verify hydraulic or code compliance.