Condensate material takeoff

Condensate Drain Material Planner

Build a transparent condensate-line material basket with separate pipe, fittings and support quantities.

Material inputs

Use actual project quantities for pipe diameter, traps, cleanouts and connection types. This page is a procurement planner.
Enter run, fittings and supports.

Material plan

Planning pipe length
—
—
—Pipe
—Fittings
—Supports
—Pipe allowance
—

Planning methodology

Pipe allowance applies only to the straight pipe quantity. Fitting spare is handled separately because fittings are discrete items.

Pipe planning = run × (1 + pipe allowance ÷ 100)
Fitting planning = ceiling(fitting count × (1 + spare ÷ 100))

Worked example

A 15 m run with 5% allowance produces 15.75 m of planned pipe. Six fittings with 10% spare round up to 7 fittings.

Why separate quantities matter

A single overall waste percentage can hide a shortage in fittings even when linear pipe quantity looks adequate.

Frequently Asked Questions

Does this calculate support spacing?

No. Support count is entered separately.

Does it choose pipe diameter?

No.