Compaction planning

Soil Shrinkage Calculator

Estimate how much a loose soil quantity represents after compaction. Compare compacted volume, volume loss and the loose material needed for a target finished volume.

Soil quantity inputs

Use the shrinkage relationship that matches the project's material and compaction basis. This simple percentage model is not a substitute for field density testing or specification requirements.
Enter loose volume and shrinkage.

Compaction volume result

—
—
—Loose input
—Volume loss
—Loose required for target
—Compacted mass
—

How soil shrinkage is estimated

If a selected shrinkage percentage is being used as a simple volume model, the compacted quantity is the loose volume reduced by that percentage.

Compacted volume = loose volume × (1 − shrinkage ÷ 100)
Loose quantity for target = target compacted volume ÷ (1 − shrinkage ÷ 100)

Worked example

600 m³ of loose material with a 15% assumed shrinkage becomes 510 m³ of compacted volume in this simplified model. To obtain 500 m³ compacted, the corresponding loose quantity is about 588.24 m³.

Why terminology matters

Earthwork specifications may use compaction factors, shrinkage factors, densities or measured volume relationships. Do not mix definitions from different project documents.

Why field verification matters

Actual placed volume depends on moisture, material gradation, lift thickness, compaction equipment and achieved density. A percentage calculator is most useful for planning and scenario comparison.

Frequently Asked Questions

Does shrinkage reduce volume?

In the simplified model, yes.

Can I calculate material for a target compacted volume?

Yes.

Is shrinkage universal?

No.

Does this replace field testing?

No.